Old Road Blackspot Funding ImprovementsMooney Mooney to Somersby.
North of the Hawkesbury River Bridge within Gosford Shire
$750,000 has been allocated to make engineering upgrades to improve safety. 7 locations have been identified, the planning for 6 of these locations has been finalised and the details are attached. The improvements have been substantially completed at 3 of these sites.
The planning for the remaining location should be completed soon.
Please note that the Locations as described are not the same as the Council Work Zones and Work Sites numbers that appear on the drawings and plans. We have used the term "Location" for ease of numbering to describe a trip North along the Old Road from the Hawkesbury River
- Please note that these drawings may be subject to minor adjustments.
Location 1See dowloadable plan files Loc11 to Loc13 ------>
Heading north about 1 km past Mooney Mooney, just on the Northern side of the Hawesbury River, you pass Cheero Point Road on the right and start up the hill. Site 1 is the first 90 degree right hander you come to. (about 1.2 km after Cheero Point Road)

Improvements are:-
- Resealing the surface with asphalt
- Realigning the corner
- Additional directional signs
- Rub rail under W Beam guard rail
- Painted Transverse Bars
- A wider painted median
Location 2See dowloadable plan files Loc21 to Loc23 ------>
This is the second left hander after Site 1
Improvements are:-
- Resealing the surface with asphalt
- Realigning the corner
- Additional directional signs
- A wider painted median
- Rub Rail
Location 3See dowloadable plan files Loc31 to Loc33 ------>
This is the site of at least one `head on' between 2 bikes which resulted in the death of one of the riders.
Improvements are:-
- Resealing the surface with asphalt
- Realigning the corner so it has a constant radius
- Removing vegetation from the inside of the corner to improve visibility
- Installing additional directional signs
- A wider painted median
Location 4See dowloadable plan files Loc41 to Loc43 ------>
This is the corner at the turn off to the truck weigh station
Improvements are:-
- Additional painted median
- Additional directional signs
- Rub rail under the W beam guard rail
- Caution Driveway sign
- Removing vegetation from the inside of the corner to improve visibility
Location 5See dowloadable plan files Loc51 to Loc55 ------>
The first right hand corner out of Calga when heading towards Mt White
Improvements are:-
- Resealing the surface with asphalt
- Realigning the corner ( not to constant radius )
- Additional directional signs
- Rub rail under W beam guard rail
- Painted wide median
- Improved drainage to reduce the amount of leaf litter washed onto the road

Location 6
(See dowloadable plan files Loc61 to Loc65 ------> )The first left hand corner out of Calga when heading towards Gosford
Improvements are:-
- Resealing the surface with asphalt
- Realigning the corner so it has a constant radius
- Additional directional signs
- Rub rail under W beam guard rail
- Painted Transverse Bars
In addition painted linemarking is to be refreshed along entire length of the road.